Custom home builders price a house in one of three ways. A fixed-price contract sets one number for a defined scope, and the builder absorbs overruns. A cost-plus contract pays the builder’s actual, documented costs plus a fee, and you absorb overruns. A guaranteed maximum price (GMP) contract is cost-plus with a ceiling (AIA Contract Documents). On cost-plus work, published builder fees mostly run 10% to 20% of the cost of the work (Buildern, Fox Luxury Builder). In New Hampshire, where general contractors need no state license and deposits have no legal cap, the contract is most of your protection (NH Insurance Department, NH Construction Law).
What are the main types of home building contracts?
| Contract type | How you pay | Who carries cost overruns | Standard form | Fits best when |
|---|---|---|---|---|
| Fixed price (lump sum, stipulated sum) | One agreed price for the defined scope | Builder, except for owner changes | AIA A101; NAHB Contract 101 | Plans and selections are complete and the site is known |
| Cost-plus, percentage fee | Actual costs plus a % of those costs | Owner | AIA A103; NAHB Contract 102 | Design or selections are still open |
| Cost-plus, fixed fee | Actual costs plus a set dollar fee | Owner (fee does not grow) | AIA A103 | Scope is mostly set but costs are uncertain |
| Guaranteed maximum price (GMP) | Actual costs plus fee, capped | Builder above the cap | AIA A102 | You want open books and a ceiling; drawings are near complete |
| Unit prices (often inside one of the above) | A set price per cubic yard, foot or ton | Shared: you pay for actual quantity | Clause, not a form | Quantities are unknown, such as ledge or fill |
Sources: AIA document synopses, Fox Luxury Builder on NAHB forms, NH Construction Law #136.
Fixed price
The builder agrees to build the drawn and specified house for a set sum, which covers labor, materials, equipment, overhead and profit. The contract should say when that sum can change, and any change goes through a change order (AIA). You know the number up front. The trade-off, as a New Hampshire construction lawyer puts it, is that in a tight market fixed prices “tend to be padded” to cover uncertainties, and change orders are where many fixed-price contractors earn their best return (NH Construction Law #136). One Florida builder puts that cushion at 10% to 20% above the equivalent cost-plus estimate (Fox Luxury Builder).
Cost-plus
You reimburse the builder for the cost of the work and pay a fee that can be a lump sum, a percentage or something else. Because every dollar spent is your dollar, the contract normally requires detailed records and gives you access to the builder’s books (AIA). You get transparency and flexibility, and you take on the risk.
Guaranteed maximum price
The builder guarantees the total will not exceed a set amount, plus or minus approved changes. Many GMP contracts include a bonus or shared-savings clause if the job comes in under (AIA). A GMP is only as good as the drawings behind it: one set against incomplete plans moves the argument to whatever the missing parts cost (Fox Luxury Builder).
What does a builder’s fee cover, and how much is it?
The fee pays for everything that is not a direct cost of your house: the office, management salaries, company vehicles, general insurance, accounting, software and profit (Buildern). On a fixed-price job the same overhead and profit are in the number; they are just not shown.
Published fee ranges
| Source | Range | Notes |
|---|---|---|
| Buildern (Oct. 2026) | 10 to 25% of the cost of the work | Larger homes and builders sit lower |
| Fox Luxury Builder (July 2026) | Usually 10 to 20% | Florida builder |
| BuildingAdvisor.com (2015) | 18 to 25% typical markup; 14 to 18% “more reasonable” on cost-plus | Owner takes the overrun risk, so the fee should be lower |
| Lakeview Building (Nov. 2026) | 15 to 25% typical; 12 to 18% on builds over $2.5M | Lakefront homes over $1.5M; GMP with an 8 to 10% contingency pool |
We found no published survey of builder fees in New Hampshire, so treat these as national reference points.
What NAHB’s cost survey shows
NAHB’s 2024 survey of builders broke the average new home’s $665,298 sale price into parts: overhead and general expenses were 5.7% ($38,248) and pre-tax profit 11.0% ($72,971) (NAHB). Together that is $111,219, or about 26% of the $428,215 construction cost in the same survey (our math). Those builders mostly sell houses on their own lots, so they also carry land, sales and marketing risk that a custom builder working on your land does not. That helps explain why custom cost-plus fees run lower.
What should be billed as cost, and what comes out of the fee?
| Usually reimbursed as cost of the work | Usually covered by the fee |
|---|---|
| Materials delivered to the job | Office rent, utilities, admin staff |
| Subcontractor invoices | Owner and estimator salaries |
| Field labor at agreed rates | Company vehicles not dedicated to the job |
| Site supervisor time, if the contract says so | Accounting, software, general insurance |
| Equipment rental, job-specific tools | Marketing |
| Permits, inspections, utility fees | Fixing the builder’s own defective work |
| Dumpsters, portable toilets, temporary power | Profit |
| Builder’s risk insurance |
Source: Buildern. The gray areas are supervision and the owner’s own time. A builder who bills management hours as a job cost and then adds a full percentage on top may be charging twice for the same thing (BuildingAdvisor.com). Neither way is wrong; the contract just has to say which. One lakefront-home estimate shows how much this matters: an 18% fee plus a separately billed superintendent, marked-up general conditions and retained supplier rebates added up to an effective 29.3% markup (Lakeview Building).
How do the contract types compare on the same house?
Take a house estimated at $700,000 in cost of the work with a 15% fee ($105,000). During the build you approve $50,000 in upgrades by change order, and the excavator hits ledge that adds $30,000. Final cost of the work: $780,000.
| Cost-plus 15% | Cost-plus fixed fee | GMP with ledge included | GMP with ledge excluded | |
|---|---|---|---|---|
| Fee terms | 15% of cost | $105,000 | $105,000, cap $805,000 | $105,000, cap $805,000 |
| Cap after $50,000 change orders | None | None | $855,000 | $855,000 + actual ledge cost |
| You pay | $897,000 | $885,000 | $855,000 | $885,000 |
| Builder’s fee actually earned | $117,000 | $105,000 | $75,000 | $105,000 |
Under the percentage fee, the ledge and the upgrades raised the builder’s pay by $12,000. Under the GMP with ledge included, the builder ate the $30,000. That is why, on New Hampshire lots where ledge is common, a GMP or fixed price will usually exclude rock or price it per cubic yard. A fixed-price job with ledge excluded behaves much like the last column. Our site costs guide covers how to scout for ledge before you sign.
Which contract type should I choose?
A New Hampshire construction lawyer suggests weighing these questions (NH Construction Law #136):
- Is the scope likely to change a lot? Cost-plus handles change with less friction.
- Are quantities uncertain? Unit prices for items like ledge, fill or well depth cut the risk on either contract type.
- Is the finish date critical? A busy builder may put cost-plus work behind fixed-price jobs.
- Is the budget fixed? A fixed price gives more certainty.
- Are allowances a big share of the price? Then your “fixed” price is partly cost-plus anyway.
In our view, if the plans are finished, the selections are made and the lot has been test-pitted, a fixed price is simple and works. If you are still choosing finishes or the site is a question mark, cost-plus with a not-to-exceed number or a GMP gives you open books without an open-ended bill. Pure cost-plus with no cap fits owners who trust their builder and can absorb a miss.
One trap to avoid: a contract labeled “estimate.” The lawyer above reports owners and builders who later disagree over whether an estimate was meant as a fixed price (NH Construction Law #136). New Hampshire has no statute capping how far a final bill can exceed an estimate. A grossly careless estimate can support a negligent misrepresentation claim, but no New Hampshire court has adopted a set tolerance (NH Construction Law #157). Write the guardrail into the contract instead: written approval before the estimate is exceeded, or a cap on the overage.
How do allowances and change orders work?
Allowances
An allowance is a budget line for something not yet chosen, such as tile, lighting or cabinets. If a cabinet allowance is $8,000 and you pick cabinets that cost $11,000 on the same basis, you owe at least the $3,000 difference, and installation and markup can add to it (Bean Group). For each allowance, get in writing:
- the dollar amount and what it covers (material only, or installed);
- whether the builder’s markup applies to overages;
- whether you get a credit if you spend less;
- the date you must choose by.
A construction lawyer recommends keeping allowances to materials only and itemizing them, since vague lump allowances like “flooring” invite disputes (Jordan Ramis). Low allowances can make one bid look cheaper than another, so compare them line by line.
Change orders
A change order is a signed change to the scope, price or schedule. New Hampshire courts have sometimes allowed builders to collect for extra work that was approved without the written change order the contract required, finding the requirement waived (NH Construction Law #132). Do not rely on that either way: get every change priced and signed before the work. If you have a construction loan, changes that raise the cost are usually yours to fund out of pocket, and some lenders want written notice before a change is made (St. Mary’s Bank, Savings Bank of Walpole).
How much deposit should a builder ask for, and how do draws work?
Deposits
New Hampshire law does not cap deposits. Massachusetts and Pennsylvania limit them to one-third of the price, and Maine does too unless the owner signs a waiver. A New Hampshire construction lawyer says any request for more than a third up front “should be viewed with skepticism” (NH Construction Law #153). The Attorney General lists a down payment over 50% of the final cost as a warning sign (NH DOJ, 2022).
In January 2026 a Stratham contractor was sentenced to 10 to 30 years in state prison for taking more than $2.4 million in down payments without doing the work (NH Construction Law #153). Ways to protect a deposit:
- ask for an itemized list of what it pays for;
- require in the contract that it be used only on your job;
- on large deposits, have it held in a separate escrow account and released against supplier invoices (same source).
Draw schedules
After the deposit, payments should follow progress, not the calendar. Lenders release construction money in draws tied to milestones such as foundation, framing, roof, mechanical rough-ins and interior finishes, after an inspector confirms the work (St. Mary’s Bank). Savings Bank of Walpole pays builders once work is complete and “highly discourage[s]” deposits before construction (SBW brochure). On a cash job, copy that discipline: pay for work in place.
How do construction loans work in New Hampshire?
Most owners building on their own land use a construction-to-permanent loan: one application and one closing, interest-only payments on the money actually drawn during construction, then automatic conversion to a regular mortgage (St. Mary’s Bank). Terms from two New Hampshire lenders’ published materials:
| Term | What NH lenders publish |
|---|---|
| Loan-to-value | Up to 95% of the completed value (St. Mary’s) |
| Construction period | 12 months (Walpole; St. Mary’s blog); up to 18 months (St. Mary’s product page) |
| Payments during the build | Interest only, on disbursed funds |
| Inspections | Before each draw; Walpole’s fee includes the first eight |
| Budget above the loan | Collected from you at closing, escrowed, and spent first (Walpole) |
| Overruns from change orders | Your responsibility (St. Mary’s) |
| Time to close | About 60 days once builder and plans are set (St. Mary’s) |
Sources: St. Mary’s Bank product page, St. Mary’s Bank guide, Savings Bank of Walpole. St. Mary’s own pages disagree on the construction period, so ask.
The lender lends against the appraised value of the finished house, not your cost. In rural New Hampshire towns with few new-construction sales, appraisals on custom homes often come in under cost, and a Grafton-area broker calls that the most common reason a construction loan gets resized late (Owl’s Nest Real Estate). Get the appraisal early and have cash for a gap. With mortgage rates above 7% this fall (NAHB, Nov. 17, 2026), a rate lock at closing matters too. Our cost guide has the numbers to build the budget the lender will ask for.
What New Hampshire laws protect you on a home building contract?
No state license for general contractors
New Hampshire does not license general contractors. The NH Insurance Department says so, noting that electricians and plumbers are regulated (NHID), and the Attorney General’s office says contractors “do not need to be licensed” (NH DOJ, 2022). The NH Home Builders Association’s consumer page says the opposite, that every contractor needs a license (NHHBA); the state agencies are the better authority here.
That may change. Senate Bill 523 as introduced in January 2026 would have required builders to register, carry insurance and post a $50,000 bond (SB 523 as introduced). It was amended into a study committee and signed July 2, 2026 as Chapter 258 (NH General Court docket). The committee’s report was due November 1, 2026, and any registration requirement would need a new bill (Hello Contractor News). As of today, nothing has changed for homeowners.
What is licensed or permitted: electrical and plumbing work must be done by NH-licensed trades unless an owner does it on the home they live in (Bethlehem permit application), and septic plans must be prepared and sealed by an NHDES-permitted designer (Env-Wq 1003.02). Our guide on how to choose a builder covers vetting when there is no license to look up.
The Consumer Protection Act (RSA 358-A)
RSA 358-A:2 makes unfair or deceptive acts in trade unlawful, including misrepresenting the quality or standard of services or claiming approvals or certifications a business does not have. Under RSA 358-A:10, a person harmed can sue for actual damages or $1,000, whichever is greater; the court must award two to three times that for a willful or knowing violation, plus costs and reasonable attorney’s fees, and any contract waiver of those damages is void. The Attorney General’s Consumer Protection Bureau takes complaints at 1-888-468-4454 (NH DOJ).
Mechanic’s liens (RSA 447)
Anyone who supplies $15 or more of labor, materials or professional design work to your house under contract with you has a lien on the house and land (RSA 447:2). A subcontractor or supplier hired by your builder gets the same lien if they give you written notice before doing the work (RSA 447:5). Once notified, you must hold back enough to pay their claim (RSA 447:8). The lien lasts 120 days after the work or materials are supplied (RSA 447:9), and an attachment securing it can take priority over a construction mortgage unless the lender shows the subs were paid (RSA 447:12-a). The practical rule: get lien waivers from the builder and major subs and suppliers with each payment, as the Attorney General’s home repair guide recommends (NH AG guide).
Insurance
Contractors with one or more employees must carry workers’ compensation in New Hampshire. The Insurance Department suggests general liability of at least $1 million per occurrence and $2 million aggregate, a certificate sent directly by the agent, a call to confirm the policy is active, and a check of workers’ comp at the state’s free verification site (NHID). Be wary of any builder who asks you to pull permits in your own name (same source).
What should I get in writing before I sign?
Start with the Attorney General’s checklist (NH AG guide) and add the terms that cover fees, allowances, site conditions and payments:
- The builder’s legal name, physical address and phone, rather than a P.O. box.
- The contract type stated plainly: fixed price, cost-plus or GMP. Never “estimate” without saying what it binds.
- Plans, specifications and a finish schedule attached to the contract.
- For cost-plus: the fee, how it applies to change orders, and the list of reimbursable costs versus fee items, plus your right to see invoices.
- Every allowance itemized, with what it covers and how overages and credits work.
- How unknown site conditions are handled: ledge, unsuitable soil, water. Unit prices are best.
- A written change order process: priced and signed before work, with the schedule effect.
- The deposit amount, what it buys, and where it is held.
- A payment schedule tied to completed milestones, matched to your lender’s draw schedule.
- Lien waivers with every payment.
- Insurance certificates and proof of workers’ comp.
- Who pulls permits (the builder) and who schedules inspections.
- Start date, completion date, and what happens on delay.
- Warranty terms, and how disputes are resolved.
- How either side can cancel, and how a refund works.
If you are in the Littleton, Franconia or Bethlehem area and want to talk through which structure fits your project, Fregeau Builders offers general contracting and can walk you through how a contract would be set up. You can also reach us here.
Sources
- AIA Contract Documents: Construction Contract Payment Methods Explained (July 8, 2026) (accessed November 2026)
- AIA Contract Documents: Document synopses by family (A101, A102, A103) (accessed November 2026)
- Buildern: Cost-Plus Contracts Explained (Oct. 22, 2026) (accessed November 2026)
- Fox Luxury Builder: Cost-Plus vs. Fixed-Price Contracts (July 28, 2026) (accessed November 2026)
- BuildingAdvisor.com: Cost Plus Contracts for New Homes (2015) (accessed November 2026)
- Lakeview Building: Cost-Plus vs. Fixed-Price vs. GMP Lake Home Contracts (Nov. 2026) (accessed November 2026)
- NAHB: Cost of Constructing a Home 2024 (Jan. 20, 2025) (accessed November 2026)
- NH Construction Law #136: Fixed Price vs. Cost Plus Contracts (June 23, 2024) (accessed November 2026)
- NH Construction Law #132: Written Change Order Requirements (Dec. 30, 2023) (accessed November 2026)
- NH Construction Law #153: Upfront Payments in Residential Construction (Jan. 24, 2026) (accessed November 2026)
- NH Construction Law #157: The Legal Effect of an Estimated Price (May 30, 2026) (accessed November 2026)
- Bean Group: Cost to Build a Home in NH, A Complete Budget Checklist (accessed November 2026)
- Jordan Ramis: Three Guidelines to Avoid Construction Allowance Pitfalls (accessed November 2026)
- NH Department of Justice: Consumer Alert on Home Improvement Scams (Mar. 10, 2022) (accessed November 2026)
- NH Attorney General: Home Repair and Improvement, What You Should Know (via Town of Greenland) (accessed November 2026)
- NH Insurance Department: How to Verify If Your Contractor Has the Right Insurance (accessed November 2026)
- NH Home Builders Association: Hiring a Contractor (accessed November 2026)
- NH General Court: SB 523-FN as introduced (2026) (accessed November 2026)
- NH General Court: Docket of SB 523 (2026), Chapter 258 (accessed November 2026)
- Hello Contractor News: New Hampshire study committee weighs statewide registration for residential builders (Oct. 26, 2026) (accessed November 2026)
- NH General Court: RSA 358-A:2, Acts Unlawful (accessed November 2026)
- NH General Court: RSA 358-A:10, Private Actions (accessed November 2026)
- NH General Court: RSA 447, Liens for Labor and Materials (accessed November 2026)
- NH General Court: RSA 447:5, Subcontractors (accessed November 2026)
- NH General Court: RSA 447:8, Account (accessed November 2026)
- NH General Court: RSA 447:9, Duration (accessed November 2026)
- NH General Court: Env-Wq 1000 rules (accessed November 2026)
- Town of Bethlehem: New Single-Family Construction Building Permit Application (accessed November 2026)
- St. Mary’s Bank: Construction-to-Permanent Mortgage Loans (accessed November 2026)
- St. Mary’s Bank: Why Building a Home in New Hampshire Could Be a Better Option (May 18, 2026) (accessed November 2026)
- Savings Bank of Walpole: Construction loan brochure (accessed November 2026)
- Owl’s Nest Real Estate: Building a New Home in New Hampshire (updated Nov. 12, 2026) (accessed November 2026)
- NAHB: Builder Sentiment Continues to Fall on Affordability Concerns (Nov. 17, 2026) (accessed November 2026)