Within 250 feet of a New Hampshire lake over 10 acres, a fourth-order or larger river, or a designated river, most construction, excavation and fill needs a state shoreland permit from NHDES (RSA 483-B:5-b). The house and attached decks must sit at least 50 feet from the reference line, the first 50 feet stays a vegetated buffer managed by a tree point system, at least a quarter of the land from 50 to 150 feet stays natural woodland, and impervious cover over 20% of the lot’s shoreland area triggers stormwater requirements (RSA 483-B:9). A dock needs its own wetlands permit. The standard shoreland permit fee is $400 plus $0.20 per square foot of disturbed area, and NHDES has 30 days to act on it.
Towns can be stricter than the state, and many are, so treat the state rules as the floor.
Does the shoreland law apply to my lot?
The Shoreland Water Quality Protection Act covers all land within 250 feet of the reference line of “public waters,” measured horizontally (NHDES Protected Shoreland FAQ). Public waters are:
- lakes, ponds and artificial impoundments over 10 acres;
- year-round rivers and streams of fourth order or higher;
- rivers and river segments designated under the Rivers Management and Protection Program;
- tidal waters.
Where is the reference line?
For lakes and impoundments, the reference line is a surface elevation that NHDES publishes in its Consolidated List of Waterbodies. For rivers, it is the ordinary high water mark on the bank (RSA 483-B:4). NHDES notes that the reference line is not the natural high water line and is not a property boundary. Your surveyor finds the elevation on the ground and draws the 50, 150 and 250-foot lines from it.
North Country waters on the list
Some local examples from the consolidated list:
| Waterbody | Town on the list | Reference line (ft above sea level) |
|---|---|---|
| Partridge Lake | Littleton | 846 |
| Moore Reservoir (Connecticut River) | Littleton | 807 |
| Reynolds Pond | Littleton | 1,041 |
| Forest Lake | Whitefield | 1,106 |
| Mirror Lake | Whitefield | 1,035 |
| Burns Pond | Whitefield | 1,016 |
| Baker Brook Pond | Bethlehem | 1,090 |
| Echo Lake (Franconia Notch) | Franconia | 1,931 |
| Streeter Pond | Sugar Hill | 914 |
| Coffin Pond | Sugar Hill | 890 |
| Pearl Lake | Lisbon | 1,017 |
| Comerford storage (Connecticut River) | Monroe | 647 |
| River | Where the Act starts to apply, per the list |
|---|---|
| Ammonoosuc River | Designated river from Lake of the Clouds to the Connecticut River, through Bethlehem, Littleton and Lisbon |
| Gale River | From the junction of its north and south branches in Bethlehem |
| Pemigewasset River | Designated segment from the outlet of Profile Lake in Franconia Notch; fourth order from Harvard Brook in Lincoln |
| Wild Ammonoosuc River | From the juncture of an unnamed third-order stream (listed under Easton) |
| Connecticut River | Designated segment from the outlet of Fourth Connecticut Lake to the Massachusetts line |
Source: NHDES Consolidated List. NHDES says the list “should not be relied upon to identify all water bodies” covered by the law (NHDES), so a pond missing from it may still count if it is over 10 acres. A lot on a river in Littleton or Bethlehem is just as covered as a lakefront lot, which surprises many buyers.
What are the setbacks and buffers?
| Distance from reference line | What applies |
|---|---|
| 0 to 25 ft | No fertilizer; beyond 25 ft, slow or controlled-release only |
| 0 to 50 ft: waterfront buffer | Natural ground cover stays except a 6-ft footpath; stumps and roots stay; trees managed by the point system; no new primary structures |
| 50 ft: primary building line | House and attached decks must be behind it |
| 50 to 150 ft: woodland buffer | At least 25% of this area kept as natural woodland |
| 75 / 100 / 125 ft | Minimum setback for a new leach field near a lake, depending on soil (75 ft for rivers) |
| 0 to 250 ft: protected shoreland | Shoreland permit for construction, excavation and fill; impervious limits; 150 ft of frontage for any new waterfront lot |
Sources: RSA 483-B:9; RSA 483-B:4; NHDES FAQ.
The waterfront buffer point system
Starting at the north or east property line, the first 50 feet is divided into segments 25 feet along the shore and 50 feet deep. Each segment is scored by tree and sapling diameter, measured 4½ feet off the ground (RSA 483-B:9, V(a)):
| Diameter | Points |
|---|---|
| 1 to 3 in. | 1 |
| Over 3 to 6 in. | 5 |
| Over 6 to 12 in. | 10 |
| Over 12 in. | 15 |
If a segment scores more than 25 points, you may remove trees as long as at least 25 remain. Example: a segment with two 14-inch pines (30 points) and three 8-inch maples (30 points) totals 60. You could take both pines and keep 30 points, or take all three maples and keep 30. You could not take the pines and two maples, which would leave 10. Dead, diseased or unsafe trees don’t count and can come out. Pruning for a view is allowed. Segments that are naturally ledge or beach get a proportionally lower requirement. Lots developed before July 1, 2008 can keep, but not enlarge, existing lawns and cleared areas in the buffer.
Impervious surface limits
Roofs (including overhangs), decks, patios, and paved or gravel driveways and parking all count as impervious unless designed to infiltrate water (RSA 483-B:4; NHDES FAQ). The percentage is measured against the part of the lot inside the 250-foot zone. Over 20%, you need a stormwater system that infiltrates the added runoff. Over 30%, the stormwater system has to be designed and certified by a professional engineer, and any waterfront buffer segment below 25 points has to be replanted.
For example, a lot with 100 feet of frontage that runs back more than 250 feet has 25,000 sq ft inside the protected shoreland. 20% is 5,000 sq ft. A 1,600 sq ft house footprint with overhangs (about 1,800 sq ft), a 576 sq ft garage, a 300 sq ft deck and 2,400 sq ft of gravel driveway add up to 5,076 sq ft. That is just over 20%, so it needs a stormwater design. Shortening the driveway or using pervious pavers designed to infiltrate can keep it under.
What permit do I need, and what does it cost?
| Permit | When | Fee / timing |
|---|---|---|
| No shoreland permit | Interior work, repairs that don’t change footprint or impervious area, a shed under 150 sq ft at least 50 ft back with no excavation, power or plumbing, well drilling, replacing a failed septic with no increase in load | None |
| Shoreland permit by notification (PBN) | Impact under 1,500 sq ft and no more than 900 sq ft of new impervious area, meeting all standards | $400 + $0.20/sq ft of impact; NHDES must accept or reject within 5 business days |
| Standard shoreland permit | New houses, additions, rebuilds and anything larger | $400 + $0.20/sq ft of impact; 30 days to approve, deny or request information |
| Wetlands permit or notification | Docks, boat lifts, beaches, bank work, retaining walls at the water | Minimum $600 for most projects since July 1, 2025 |
| Alteration of Terrain permit | More than 50,000 sq ft of disturbance partly or wholly in the protected shoreland | $5,000 for 50,000 to 150,000 sq ft in the shoreland |
| Septic approval | Any new system or increased load | $450 per system since July 1, 2025 |
| Town permits | Building permit, zoning, driveway, local shoreline overlay | Varies by town |
Sources: RSA 483-B:5-b; NHDES FAQ; NHDES shoreland application form (fee section); NHDES fee changes, July 1, 2025; RSA 483-B:9, V(d).
Impact means all disturbed area, permanent and temporary: the foundation dig, regrading, septic area, driveway and the access path for the well rig. A new house that disturbs 9,000 sq ft pays $400 + (9,000 × $0.20) = $2,200 for the shoreland permit. The 2025 state budget raised wetlands and septic fees by 50%, but NHDES says shoreland permit fees were unchanged (NHDES).
Timelines
Under RSA 483-B:5-b, V:
- NHDES has 30 days from receiving a standard application to approve it, deny it, or ask for more information.
- If it asks, you have 60 days to answer or the application is denied, and NHDES then has 30 days to decide.
- If NHDES misses a deadline, you can request a decision in writing; if it still doesn’t act within 14 days, you have a permit by default.
- Permits last 5 years, with one extension of up to 5 more.
You also have to notify the town and every abutter by certified mail and send NHDES the postal receipts. If the property is in a designated river corridor, such as along the Ammonoosuc, the local river management advisory committee gets notice too. A 2026 law (SB 527, effective July 7, 2026) reworded that notice requirement but kept certified mail to abutters for private projects (SB 527 text).
The real schedule is set by the work before filing: a survey that locates the reference line, a septic design, a site plan with impervious calculations and buffer point counts, and town zoning review. Start in winter if you want to dig in spring.
Can I rebuild or expand an old camp close to the water?
Yes, within limits. Many North Country camps sit inside the 50-foot line. They are legal nonconforming structures, and RSA 483-B:11 sets the rules.
You can repair the camp, replace it in kind, or rebuild it in place, including a new foundation, but the footprint can’t expand or move within the waterfront buffer. To expand, the footprint can grow within the buffer only if it gets no closer to the water and the property as a whole becomes “more nearly conforming,” for example by shrinking other footprints, adding stormwater infiltration, replanting, or upgrading the septic. You can also tear the camp down and rebuild, but the new building must sit farther back from the reference line than the old one.
On structures built before July 1, 1994, a deck or open porch can extend up to 12 feet toward the water. A deck or open porch that sits between the camp and the water inside the buffer can’t be enclosed or turned into living space. Any expansion that adds sewage load needs a new NHDES subsurface approval.
NHDES says maintenance, repairs and even vertical expansion of a legal nonconforming house need no shoreland permit if the impervious footprint doesn’t change, living space doesn’t expand, and there is no excavation or fill (NHDES FAQ). A second story on an existing camp can qualify. A new frost wall foundation under it does not. Our guide to converting a camp to a year-round home covers the septic and insulation side.
Weigh the cost of moving back. Rebuilding farther from the water often means a deeper foundation in new ground, a longer septic run and more ledge. Price both options, and see our site costs guide for what that work runs.
What are the rules for docks?
A dock, boat lift or boathouse needs a wetlands permit or notification from NHDES, separate from the shoreland permit. NHDES’s reasoning: the state owns the bed of lakes and ponds over 10 acres, so a private dock sits on public land (NHDES Docks FAQ).
| Shoreline frontage under 75 ft | 75 ft or more | |
|---|---|---|
| Lakes and ponds under 1,000 acres | 4 × 24 ft, seasonal only | 6 × 30 ft, seasonal only |
| Lakes and ponds 1,000+ acres | 4 × 24 ft, seasonal or permanent | 6 × 40 ft seasonal, 6 × 30 ft permanent |
| Navigable rivers | 4 × 24 ft, seasonal only | 6 × 30 ft, seasonal only |
Source: NHDES Docks in Non-Tidal Areas FAQ.
The simplest route is the seasonal dock notification. The NHDES fact sheet lists the conditions: a lake or pond, the only dock on the frontage, at least 75 feet of frontage, at least 20 feet from the side property line and its extension over the water, out of the water at least five months a year, narrow and perpendicular to shore, and no regrading of the bank. The rules allow two boat slips per 75 feet of frontage and one more for each additional 75 feet (Env-Wt 513.12).
Fees for permitted docks went up July 1, 2025: a $600 base fee for shoreline structures, plus $3 per sq ft for seasonal docks or $6 per sq ft for permanent ones, with a $600 minimum (NHDES). A 6 × 30 seasonal dock is 180 sq ft, or $540 in area fee.
On a hydro reservoir like Moore or Comerford, read the deed for flowage rights before you plan a dock. An older NHDES dock form listed both among the waterbodies over 1,000 acres, which allow the longer seasonal dock (NHDES seasonal dock form, 2010).
How close to the water can a septic system be?
New leach fields near lakes must be at least (RSA 483-B:9, V(c)):
- 125 feet where the downslope soil is porous sand and gravel that percs at 2 minutes per inch or faster;
- 100 feet where a restrictive layer is within 18 inches of the surface;
- 75 feet in other soils, and from rivers.
Replacement systems must meet those setbacks “to the maximum extent feasible.” A new system on an undeveloped lot, or a bigger one because the house is growing, also needs a shoreland permit. Replacing a failed system with no added load does not (NHDES FAQ). Septic applications in the shoreland have to include photos of any part of the woodland buffer that will be disturbed.
Buying a developed waterfront lot
Since September 1, 2024, the buyer of developed waterfront property must have a licensed septic system evaluator inspect the system before closing if any part of it is within 250 feet of the reference line (RSA 485-A:39). If the system has no state approval, or was approved before September 1, 1989, a permitted designer must also check the leach field’s separation from the seasonal high water table. A failing system must be replaced within 180 days of closing. A buyer can skip the evaluation by committing to replace the system within 180 days (NHDES SSB-14). This replaced the old seller’s site assessment. If you plan to tear down and rebuild, budget the new system in your offer. Our land buying checklist covers the rest of the due diligence.
What changed in 2024-2026?
| Effective | Change |
|---|---|
| Sept. 1, 2024 | Waterfront septic evaluation by the buyer replaces the seller’s site assessment (HB 1113, RSA 485-A:39) |
| Jan. 1, 2025 | Fines of up to $5,000 per violation now apply to anyone who fails to restore a violation within one year of NHDES notice; the old test was a “good faith effort” at restoration (HB 1103) |
| July 1, 2025 | Wetlands and septic fees up 50%; shoreland permit fees unchanged |
| Aug. 25, 2025 | Interim rule moves threatened and endangered species screening for shoreland applications from the Natural Heritage Bureau to NHDES ($50 DataCheck fee) |
| Jan. 1, 2026 | Contractors who supervise or do work that violates the Act face fines of up to $5,000 per violation, doubling for repeat offenses (SB 299) |
| July 7, 2026 | Abutter and municipal notice wording revised (SB 527) |
Sources: NHDES, Sept. 2024; HB 1103, Chapter 218; NHDES fee changes; Env-Wq 1406.12 rulemaking notice; RSA 483-B:18; NH LAKES 2025 session summary.
The core setbacks, buffers and impervious limits in RSA 483-B:9 have not changed since 2017. A 2025 bill to raise the general fine to $15,000 (HB 422) was killed in the House.
The contractor penalty affects owners too. Clearing the buffer or regrading without a permit now exposes the excavator and builder as well as the owner, and a buyer who knew of a violation can be held liable for restoring the land (RSA 483-B:18).
What order should you do things in?
- Confirm jurisdiction. Check the consolidated list and NHDES maps, and call the town about any local shoreline overlay or larger setback.
- Get a survey that shows the reference line and the 50, 150 and 250-foot lines, plus existing trees in the buffer for the point count.
- Dig test pits for the septic, keeping clear of the first 75 feet unless the designer needs to test a replacement area there.
- Site the house behind 50 feet and wherever the septic, well radius and driveway fit. Calculate impervious area before the floor plan is final.
- File the shoreland permit, septic application and any wetlands or dock filing, with abutter notices.
- Get the town building permit.
- Install erosion controls first. Silt fence and a stabilized access path go in before the excavator digs. A temporary 12-foot construction path through the buffer is allowed but must be restored afterward unless the lot is reachable only by water.
Mistakes that cost money
- Cutting trees or pulling stumps in the first 50 feet before the permit, then paying to replant.
- Forgetting that gravel driveways and roof overhangs count as impervious.
- Designing an addition that encloses the porch facing the water.
- Assuming a river lot is exempt. The Ammonoosuc, Gale and Pemigewasset all carry the 250-foot zone.
- Buying a camp without pricing the septic replacement the 2024 law may force.
If you’re planning to build or rebuild on a lake or river around Littleton, Bethlehem, Franconia or Lincoln, we can walk the site with you and your surveyor before the design is set. See our custom homes page or contact us.
Sources
- NH General Court: RSA 483-B:4, Definitions (accessed November 2026)
- NH General Court: RSA 483-B:5-b, Permit Required; Exemption (accessed November 2026)
- NH General Court: RSA 483-B:6, Other Required Permits and Approvals (accessed November 2026)
- NH General Court: RSA 483-B:9, Minimum Shoreland Protection Standards (accessed November 2026)
- NH General Court: RSA 483-B:11, Nonconforming Structures (accessed November 2026)
- NH General Court: RSA 483-B:18, Penalties (accessed November 2026)
- NH General Court: RSA 485-A:39, Waterfront Property Transfer; Septic System Evaluation Required (accessed November 2026)
- NHDES: Protected Shoreland FAQ (accessed November 2026)
- NHDES: Protected Shoreland (accessed November 2026)
- NHDES: Consolidated List of Waterbodies Subject to the Shoreland Water Quality Protection Act (accessed November 2026)
- NHDES: Shoreland Permit Application form NHDES-W-06-037 (rev. 2023-12), as filed with the Town of Hampton (accessed November 2026)
- NHDES: Fee changes included in the 2026-2027 state budget (accessed November 2026)
- NHDES: Docks in Non-Tidal Areas FAQs (accessed November 2026)
- NHDES: WB-19, Permitting for Private, Non-Commercial Freshwater Docking Structures (accessed November 2026)
- NH Office of Legislative Services: Env-Wt 500, Project-Specific Requirements (docking structures) (accessed November 2026)
- NHDES: Seasonal Dock Notification Form for Lakes and Ponds (2010), as hosted by Winnipesaukee Builders (accessed November 2026)
- NHDES: Waterfront property transfers now require septic evaluations (September 6, 2024) (accessed November 2026)
- NHDES: SSB-14, Transfers of Waterfront Properties with Septic Systems in the Protected Shoreland (2025) (accessed November 2026)
- NH Office of Legislative Services: Rulemaking Notice 2025-202, Env-Wq 1406.12 (accessed November 2026)
- NHLA Bill Review: SB 527 (2026), Chapter 67, text of changes (accessed November 2026)
- NHLA Bill Review: HB 1103 (2024), Chapter 218 (accessed November 2026)
- NH LAKES: New Hampshire 2025 Legislative Session, Lake Protection Highlights (accessed November 2026)